Barage Complect Ltd. has completed construction of and commissioned three sites on the grounds of Beloizvorski Tsiment AD, these being: “Reconstruction of the silo feeding systems No. 13, 14 and 15”, "Vehicle loading area for bulk cement”, “Coal grinding plant, coal unloading complex, covered warehouse and transportation of coal”, “Covered warehouse for limestone - reconstruction and extension”. At the present moment the following sites are under construction: “Feeding systems for cement mills 1 and 2”, “Delivery and installation of silos for cement additives”, “Reconstruction of the filter of 2nd cement mill”, “Clinker cooler 2 dusting system – reconstruction”, etc.
Work on the site “Coal grinding plant, coal unloading complex, covered warehouse and transportation of coal” included construction and installation works such as:
Installation and start-up and commissioning works of technological equipment have been implemented on the site, including for:
The execution of the contract for site "Vehicle loading area for bulk cement” starts to run from the beginning of May 1999. Barage Complect Ltd. has carried out the following construction and installation works:
Installation and start-up and commissioning works of technological equipment have been implemented on the site, including for:
At the present moment, the following site is under construction: “Warehouse for limestone – extension and reconstruction”. The execution of the construction constitutes completion and reconstruction of stage ІІ of the warehouse for raw material and construction of an entirely new one – stage ІІІ with an additional length of 108.80 m. The extension is envisaged to be with 18 new axes, extending south of the existing warehouse.
For this purpose, the already built metal construction is being used from axis No. 49А to axis No. 63 and a new extension is being made from axis No. 64 to axis No. 81 with the same constructional solution. The load-bearing metal construction of the three stages is identical. The warehouse will be equipped with new technological equipment, using which the loading and unloading of the raw material, delivered by SHADE, will be carried out.
The construction and installation works of the site include:
Work on the site shall be conducted in two stages. The first stage shall include:
1. Reconstruction of inlets of mills and construction of new silos for additives, including:
2. Reconstruction of a mill outlet and filters as per project of SCHEUCH. The second stage includes reconstruction and repair of a drum and mill drive systems.
The project includes replacement of an existing multi-cyclonic filter with a new sleeve filter, preceded by a heat exchanger for reducing the temperature of the gases going into the filter for purification. The heat exchanger is equipped with eight axial fans, situated in 2 columns. From the fan, the gases rise up to 40.45 m through a chimney with a 2,800 mm diameter. The chimney has a reinforcing truss structure and the obligatory deflector. The winking valves under the sedimentary hopper and the hopper under the chimney are also being replaced with new double ones with emergency operation.
The technological equipment, installed on the site “Clinker cooler 2 dusting system”, is made and delivered by the company REDECAM – Italy. The newly installed chutes with winking valves between the hopper and the reddler are made and delivered by the company Zorini OOD. Balkanstroy AD has performed the installation of the following technological equipment: